Skip to Content
0
Former Member
Sep 27, 2010 at 05:16 PM

Availability Date calculation in SNP Heuristics

97 Views

Dear Experts,

I am using weekly bucket profile. In the SNP PPM, period factor is set as 0. Lets say I create a PIR on date 09.11.2010 which is Tuesday.

If I run Location Heuristics, it should schedule the Planned Order on 08.11.2010 12:00. But system is scheduling it on 11.11.2010 23:59:59 i.e. Thrusday. No matter on which day I create the PIR, it somehow always schedules it on Thrusday. Please help to understand how it is happening.

(Though it should not matter here but Location-Product data also has period factor as 0)

Regards

Rinju

Edited by: Rinju Mukherjee on Sep 27, 2010 7:38 PM