on 09-27-2010 12:27 PM
Dear Experts,
We are using SAP-Ps in construction Indus. We are facing one problem in progress analysis (CNE1 & CNE5).
We have selected method for plan it is "Time" & actual it is also "Time". After running the cne1 the report CNE5 is showing BCWS & BCWP only for 1 wbs. Rest for all WBS it is blank. This is happening for the first time in our project, for earlier projects system is showing values in BCSW & BCWP.
What will be reason behind this is it system error or somthing else.
Thanks & regards,
Prashant
Can you please check this notes, hope this will solve your issue:
Note 189230 - Progress analysis - FAQ
Note 129200 - Various errors in Progress Analysis
Regards,
ahs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Parab,
of course, you've made sure that the progress version is maintained in the object, isn´t it?
Is POC missing as well?
Thanks
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.