Assigned Value

Dear SAP Expert ,

Is there any way to get the assigned value via Z-Program and how to get it technically ? , Actually I have a requirement to develop a download program to the end users , as you know that the assigned is calculated by (Actual + Commitment + Rem. Order Plan ) .

Thanks

Edited by: Khalid Boudi on Sep 27, 2010 7:57 AM

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on Sep 27, 2010 at 06:24 AM

    Assigned values are calculated when you execute a report, I dont think it will be available in table, IF you want to prepare a report which requires assigned value, then follow the logic which calculates assigned value in a hierarchy report.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 27, 2010 at 06:24 AM

    Hi Khalid,

    Although i have not tried this, i think it is possible to achieve this. I would suggest you check the tables that store these costs ( Actual,Commitment,Rem. Order Plan) and fetch them from these tables to develop the required Z-Program. Just to start off you can check the tables COSS, COSP, RPSCO etc.

    You can also search the forum for the relevant tables to build this program.

    Regards,

    Gokul

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Mohamed Rafi

      Considering the above explanation, it is not a matter of the money being trapped as RemOrderPlan.

      Please review note 178837 with regards to availability control.

      The residual order plan is calculated depending on the assigned network, network activity or order.

      With the status 'Released', the residual order plan is always included in the assigned value.

      With the status 'Created', this applies only if the 'Assign Funds in Plan' indicator is set (transaction OPSV) in Customizing for the network type or order type.

      Exception: The residual order plan of networks or network activities that are used for forecasts (see relevant indicator in the network type, transaction OPSC) is never included in the assigned value.

      With the status 'technically complete', 'complete' or 'deletion flag', the residual order plan is never included in the assigned value.

      The plan values of assigned networks are not taken into account for valuated project stock.

      If you set the availability control to validation against annual values, the values planned at year level are taken into account provided there is no overall plan value.

      regards,

      ahs

  • Posted on Oct 07, 2010 at 09:38 AM

    Hi

    check the FM in se37 - AIPR_GET_VALUE_TABS or FMs with AIPR* which may be useful to get value (I hope you may get as per value types).

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.