After conversion SNP planned order to PPDS planned order repet mfg appears

Dear All,

After i convert SNP to PPDS planned order and data is sent to R3, in R3 planned order "repetitive manufacturing" indicator appears.

How to avoid such indicator to be ticked automatically?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 24, 2010 at 04:08 AM

    Hi,

    Check in Material Master in MRP 4 View whether REM allowed indicator is activated. and any REM profile is assigned.

    Thanks,

    nandha

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 24, 2010 at 08:52 AM

    Yes...if you are using REM scenario then it should be OK to have REM orders in R/3.