on 09-23-2010 6:17 AM
Dear Experts,
Is it possible to change the maintenance strategy in task list header? This field is found disabled.
If yes, then how and is there any mass change transaction available.
Regards,
Tushar
Try removing all Packages from the operations
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
After Removing the pacakges from Task List operations Then Remove the Same Task List from Maintenance Plan In which, You are using the same task List .Then you can Remove the Strategry from the Task List Header(Then maintenance stratergy field will become editable).
For Mass Change of this You have to Go for LSMW Rcording Method .create The Two Object For this.
One is Remove the Task List From The Maintennace Plan
Second One is Removing the Packages from Task List Operation.
Regards,
Rakesh
Edited by: RAKESH ASHOK MANE on Sep 23, 2010 9:15 AM
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Tushar,
I have a small query. Why do you want to change the maintenance strategy in task list header?
If you want to change the maintenance packages for each operation, then you can do the changes in IP11. Same changes will automatically start reflecting in task list with immediate effect. Then select the necessary check box.
There is no need of mass change in maintenance strategy.
Simply make changes in IP11. I have tested it in IDES. It is working.
Please give some more information of requirement if my answer is not sufficient.
Regards,
Vaibhav Mishra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.