Dear ALL,

I have one scenario.

My client is commodity company.

They are daily procuring the material from the vendor & they have created one PO for monthly procurement but daily the price of the material is varies & They have agreement with vendor that procurement should be done on daily unit price basis.

They want to follow normal procurement process. Now how to map this scenario ?

Please help me to map this scenario.

Regards

SKK

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 22, 2010 at 11:29 AM

    Hi,

    Use scheduling agreement instead of purchase order and have time dependent conditions for the scheduling agreement.