MD04 and CO09

Hi,

Could you tell me difference between transaction MDp4 and CO09 ?

how these transaction can be used?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 22, 2010 at 08:38 AM

    Hi,

    MD04 displays only the requirements, the CO09 displays the availability situation.

    therefore there is a difference what date is displayed.

    in MD04:

    a) from issuing plant perspective: mbdat of the required schedule line

    b) from receiving plan perspective: GR date of the confirmed schedule line

    in CO09 both required and confirmed schedule lines are displayed on issuing plant side.

    br, Gabor