MD04 and CO09

Former Member
0 Kudos

Hi,

Could you tell me difference between transaction MDp4 and CO09 ?

how these transaction can be used?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

MD04 displays only the requirements, the CO09 displays the availability situation.

therefore there is a difference what date is displayed.

in MD04:

a) from issuing plant perspective: mbdat of the required schedule line

b) from receiving plan perspective: GR date of the confirmed schedule line

in CO09 both required and confirmed schedule lines are displayed on issuing plant side.

br, Gabor