Hi,
I read the SAP help portal on the topic forward scheduling for external procurement., there is this point....
Materials that are planned using MRP or forecast-based planning are switched to forward scheduling if the start date calculated in backward scheduling was in the past..
Do you understand what SAP trying to say on above point? an example will be great.
tuffy
Dear Tuffy,
Say for example
when running MRP it does backward scheduling
If the material required date falls before ( i.e 20-09-10 ) ( previous date )
Taking all parameters (PR processing time, Planned delevery time, GR processing time )
Then MRP automatically does Forward scheduling starting from current date ( i.e start date 22-09-2010 )
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Tuff ,
If you maintain Start Date in the Past ( no of days MRP system will consider as start date in past ) in OPU3/OPU5 -Define Scheduling Parametrs , then this particualr case will happen.System will carry out Forward scheeuling instade of Backward scheuling even MRP bu default does Backward .
Please try in the Sand box by keeping some work days in that Filed , Create Demand whos requirement date will be in the past and chek the MRP result after carrying out MD03.I hope it will be more clear to in this way .
Hope this is helpful .Try and revert back
Regards
JH