How do we add new MRP controller for a material in material master

Former Member
0 Kudos

It was defined in MM02? I tried mm01 which says material has already been maintained?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Siddu,

If the requirement is to change the MRP controller then directly do it in MM02

If you want to create new MRP controller then create it in OMD0 and then assign it in MM02

Regards

Madhu

Former Member
0 Kudos

Siddu,

If you have already created the MRP views for the material, then you must use change mode (MM02). You can overstrike the existing MRP controller and then save the changed record.

If the 'new' MRP controller does not yet exist at all in that plant, then you must first create the MRP controller in Configuration. OMD0.

Regards,

DB49