Task list not getting copied in Order

Hi All,

I have created a Maintenance plan where my call object is notification. I have scheduled the plan & i got the Notification after releasing the call.

I am getting the Task list reference in Maintenance plan tab in notification.

Now my issue is, the task list is not getting copied to order when i create order against the notification.

Kindly help me resolve the issue.

Thanks & regards,

Basavaraj

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 21, 2010 at 05:49 PM

    Basavaraj,

    When a order is created from the worklist (IW28) of notification , the task list associated to the notification will be exploded and added as operations.

    Have a look at [Sap Help|http://help.sap.com/saphelp_erp60_sp/helpdata/en/fc/f26c3c17c8c67ee10000000a11402f/frameset.htm]

    for detailed steps.

    Regards

    Narasimhan