Purchase requisition query

Former Member
0 Kudos

Hello All,

I have a requirement from different sources on the same day 01.10.2010, but due to rescheduling date proposed to expedite , the PR generated is split n i get 4 PR with the same delivery date but different rescheduling date. Is there any possibility to club these PR into one? or Can we have a sum qty when a PO is raised (single line n not multiple lines) as the delivery date and the vendor are the same. We do not want to use the lot size concept.

Regards

Divya

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This message was moderated.

Answers (1)

Answers (1)

dipak_kumar3
Active Contributor
0 Kudos

Hi,

Create 4 different line items in PO with reference to your 4 PR.

And maintain different delivery schedule in delivery schedule tab of PO. It solves your problem, I guess.

If something else is required. Get back.

Thank you!

Dipak