Hello All,

I have a requirement from different sources on the same day 01.10.2010, but due to rescheduling date proposed to expedite , the PR generated is split n i get 4 PR with the same delivery date but different rescheduling date. Is there any possibility to club these PR into one? or Can we have a sum qty when a PO is raised (single line n not multiple lines) as the delivery date and the vendor are the same. We do not want to use the lot size concept.

Regards

Divya

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 21, 2010 at 03:12 PM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 21, 2010 at 03:07 PM

    Hi,

    Create 4 different line items in PO with reference to your 4 PR.

    And maintain different delivery schedule in delivery schedule tab of PO. It solves your problem, I guess.

    If something else is required. Get back.

    Thank you!