Latest Start and Requested Edn

Former Member
0 Kudos

Hi,

I know clearly about latest end and requested start.

Why again we need latest start and requested end ?

Accepted Solutions (1)

Accepted Solutions (1)

former_member185167
Active Contributor
0 Kudos

You don't need them, they are there if you want them.

Latest start = time that you want work on the workitem started by

Requested end = a "soft" latest end