on 09-21-2010 10:11 AM
Hi guys,
I have to perform homogenous system copy from PRD to QAS.
My PRD is ECC6.0 EHP4 release 701 sp 103( SAP_basis) with oracle ver 10.2.0.4.0.
Is there any specific procedure for EHP4 or i can follow the below mentioned guide.
https://websmp204.sap-ag.de/~sapidb/011000358700000514722009E.pdf.
What pre-requisite i need to take care before doing the system copy?
Regards
Abhishek
Hi,
All pre-requisite is there in system copy guide.Apart from that take user master backup of quality system and after system copy, import the user master data back so that you have same users in quality system.
Also, take RFC's backup also.
Thanks
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.