to consider part of plant available stock

hello all,

May I know where in the SPRO configuration in SAP to tell the system what stock type (i.e. UU stock, QI, block, stock-in-transfer, restricted stock, etc) to

consider or not consider as available plant warehouse stock during MRP run for the Net Requirement Calculation? Thanks.

Tuffy.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    Sep 21, 2010 at 06:19 AM

    Dear

    May I know where in the SPRO configuration in SAP to tell the system what stock type (i.e. UU stock, QI, block, stock-in-transfer, restricted stock, etc) to :

    Goto OPPQ-Enter Plant Code -Selecty Available Stock option -Mark the check Box if you want to conside those stock ( Stock in Transit-Block Stock -Unrestricted Stock ) in Net Requirement Calcualtion .Other wise , keep it uncheked if you do not want any stock like Block Stock , in MRP NRC .

    At the same , check if you have OPJJ -Scope of check -for availablity with various stoks and Inward/outward movements , is correctly in place .

    Regards

    JH

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 21, 2010 at 06:09 AM

    HI

    Check T code OPPQ maintain plant parameters> avialable stock

    Regards

    Anupam Sharma

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 21, 2010 at 06:09 AM

    In OPPQ- Avaialble stock- U can check the required field to consider MRP

    For unrestricted stock and quality stock there is no such setting System will automatically consider the stock during MRP