Hi Gurus,

I have a weird problem. I have created a release strategy for PO with characteristics: Order type, purchasing group and total amount.

When I create from ME21 or ME21N directly, the PO has the strategy. But when I create a PR and then I use it for create a PO, the PO has no the strategy. Why? Do I have to do something else?

I hope you can help me.

Thanks in advance.

J. Garibaldi

Edited by: J. Garibaldi on Sep 20, 2010 4:23 PM

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 20, 2010 at 09:27 PM

    Hi,

    First check what are all your characteristic values for PO release strategy.

    Check those values are maintained in CL20N transaction or not.

    Now you create PO from the PR, I am sure there are / is value which is not there in PR, and when you create PO those values will not get populated to your PO. And if those values are not getting populated, system will fail, when it matches with release characteristics. Check the release characteristics with PO field values.

    So do this basic check.

    Thank you,

    Dipak