Material Movement from "Project Stock" to "Unrestricted Stock" (including cost)

Former Member
0 Kudos

Hi all,

We meet a problem.

Due to a mistake purchasing buy twice a stock for a project.

We decided to move the duplicate stock from "project stock" to "unrestricted stock" in order to make this duplicate stock available for an other projet (for example).

But, even if the stock is well "unrestricted" and not affected to our project, we still have it cost visible on our project (transaction code S_ALR_87013542).

Could you help us ?

Thank you by advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

sanjeevc
Active Contributor
0 Kudos

if material is valuated and have in project stock then it will show cost in project report, so revers the movement so that cost could be reduce from project. 2nd option if you need it for next task then you can transfer stock wbs to another wbs cost would be display on another wbs.

JL23
Active Contributor
0 Kudos

The movement is valuated at the price available in your material master since it is a reversal movement. If you had no price in the material master when the movement was done, then you did not reduce any value from the project.

Cancel your movement, enter a price in the material master and redo your movement.