How to control the confirmations using the relationships?

Hi All,

I have a requirement, there are 3 activities in the network 10, 20 and 30 and each of these activities are linked with relationship type FS.

My requirement is unless i confirm activities 10 and 20 the system should not allow me to confirm the activity 30.

Can anyone suggest how to control this?

Add comment
10|10000 characters needed characters exceeded

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 20, 2010 at 12:23 PM

    In network confirmation parameters for prdertype and plant, OPK4 maintain the check 1)Operation Sequence: Error when operation sequence is not adhered to.

    Regards,

    mahendra

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      I think you can use 'enhancements' for network confirmations. You can control this with user exits. To know exactly which user exit will be applicable,contact your ABAP consultant.

      Regards,

      Mahendra Dighe