In the production order, there is a bom with the finished goods and co-product. When doing confirmation, there is no goods movement posted.

The settlement rule is automatically assigned to order items with percentages.

When performing settlement (before TECO), there are no accounting postings ie only controlling postings to order item level. When performing settlement (after TECO), there are postings to variances (the full costs of production).

For normal production (without co-products), there are material movement postings during confirmations as well as settlement.

Anyone know how it works for co-products?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

1. For a CO- Product .. BOM should have the CO-Product Tick .

2. Both the FG and Co_product Should have a Co Product Tick in the materal master .

3. Souce Structure should be created in transaction OKEU and the percentages as per structure should be maintined in the main products( material master).

4. In Process Order BOm, the co-product should be specified as -ve quantity .

5. If all the things are maintained , during GR of Process Order , you will receive both the FG and Co-Product .This part is only difference , there is no different in settlement process w.r.t normal goods.

Kindly revert back with things you have maintained and for any further clarifications.

Regards

Sarada S Sil

Former Member
0 Kudos

Checked all as you've mentioned, but no difference during posting of CO11N (confirmation). Somehow, those flagged as co-products in the PP order BOM, do not appear in the confirmation goods movement (no posting of GR). The co-products are defined with movement type 101 in the bom.

This is different from the normal PP order confirmation where the finished goods are posted with movement type 101, no problem.

Former Member
0 Kudos

Please try to do the following :

1. In the Production Order .., check the BOM. See wether the co-product is mentioned as -ve quantity .

2. In BOM in the Po is fine.. then instead of doing confirmation with Co11N , try using transaction MB31 to receive goods for order . Use Mvt type 101 to receive the goods.. CO-product should be shown as defacult GR.. when we execute MB31..

Kindly get back if you still have problems .

Regards

Sarada

Former Member
0 Kudos

I apologize for interrupting the flow of this thread. I also have found that co-products react very differently than normal Planned Production (PP) orders. In our situation, all of the ticks inidicated are required, Material Master, BOM, etc. Also, the negative qty for the BOM is reflected as described.

The difference is definitely there when receiving the products (both parent and co-product) into inventory stock. The receipt or delivery exists for FI purposes (dr inventory and cr mfg offset), but no posting occurs in the order. It is like the order credit posting is hidden from the view of CO. At month end, we run two settlement programs. One just for co-products (CO8A or CO8B for preliminary co-product settlement) and the normal CO88 settlement. Once the settlement happens, the order then goes to zero. The variances are distributed to the specific variance accounts and everything is again in balance. This works well, but researching and viewing it can be confusing. I seem to recall a co-product report that shows more detail than KOB1 but I can not find the t-code. You can search notes regarding co-products to find several features and tips. If you use co-products, make sure you also use the program "MLCSS_KO88_TREATMENT" for the unusual error message that happens rarely.