Hello Friends,

I want system to create the stock transfer order while taking the MRP Run.

For that i know that we have to create the plant as vendor from were we are going to get that material.

With these we have to maintain the special procurement key 40 in material master of material in plant were it needed and in that you have to mention the plant from were you are getting the material.

Apart from these what are the other settings we have to do ?

Kindly let me know the process, if any one knows. I know that its not pp issue, than also if any one knows than plz share the knowledge.

Thanks and Regards,

Jitendra Chauhan

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 16, 2010 at 09:39 AM

    hi...

    u can create STO in me21n .

    issue material in migo with 561 movement type

    then gr against po in mogo with mov type 101.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 16, 2010 at 10:27 AM

    Dear,

    You need to maitain Special Procurement key "40" for the material in Plant 1. The defination of the special procurement key in "OMD9" transaction should be such that in Plant1, Special procurement key 40 , Procurement type "F", Special Procurement "U", Special Procurement Plant 0002.

    The after MRP PR will be created then you need to convert PR -> STO at planning plant.

    Please refer the below help link with example,

    system automatically creates a planned order for stock transfer or a stock transport requisition in plant 0001 and a release order for the planned order or purchase requisition in plant 0002.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 30, 2010 at 02:41 PM

    i am closing this thread

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.