If I have the following scenario:

1. Purchase Order on system for 10 widgets with a delivery date of 1st October

2. New Sales Order for 5 widgets entered with a Delivery date of 20th September

3. On running MRP wizard, it suggests we need to order 5 widgets to satisfy Sales Order as 10 on order will not be delivered on time.

Is it possible for MRP not to suggest the creation of the PO for 5 widgets?

Regards,

Juan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Sep 16, 2010 at 01:20 AM

    Hi,

    Try to use the planning horizon in MRP to avoid the suggestion

    JimM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 22, 2010 at 01:04 AM

    Unfortuantely, SAP does not handle MRP in this way. We were forced to write our own planning module which works very well in this way. If want more information let me know

    Add comment