Dear All,

When I try to split the Activity Independent Costs among various activity types ,Independent costs are being splitted equally among the activity types,even though I have selected splitting method as 12 (i.e. Activity Quantity) while configuring the splitting structure.

Actually the system should have splitted the independent costs based on Activity qty instead of splitting the costs equally.

Please help me out as how get the splitting of costs based activity qty.

Regards

Su

Accepted Solutions (0)

Answers (1)

Answers (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi Subbu

Did you assign your cost centers to the splitting structure?? The cost center for which act price is calculated must be assigned to this splitting structure

OKES and OKEW are the T codes.. In one T code you define spl structure and in another you do the assignment of cost centers

Regards

Ajay M

kandati_subramanyam
Participant
0 Kudos

Dear Mr .Ajay M,

I have already assigned required cost center to the splitting structure.

My issue is relating to splitting of costs equally instead of splitting the costs based on activity qty (i.e.12),which is the standard SAP method for splitting of costs based on activity qty.

Please suggest.

Regards

Su

ajaycwa1981
Active Contributor
0 Kudos

Hi

Your splitting structure has 2 parts

1. Where in you define rule.. here you defined rule based on 012 (Qct Qty)

2. You create Assignments and assign your splitting rule here... I hope you have assigned the splitting rule here in the assignments

3. I hope the fiscal year from which you assigned cost centers to splitting rule in OKEW is also in line

4. Also check if you defined your target cost version in case you are doing splitting based on actual cost (KSS2)

5. Also, in splitting rule, I hope you have assigned a cost element group containing all your cost elements to this group and also your activity types between whom the costs are to be split up (In the tab "Selection for assignment)"

Once you do this, activity indep costs split based on act qty only... (KSS2/KSS4)...

Regards

Ajay M

kandati_subramanyam
Participant
0 Kudos

Dear Mr Ajay,

I have done config.already w r t all the points mentioned in your mail ,but still activity costs are being splitted equally instead of activity quantity.

Please suggest anything which I have missed out to get the costs splitting based on planned qty.