on 09-14-2010 9:04 PM
Hi all,
I'm facing a problem here when executing MRP.
System is ignoring a existing PR for a material and generating a new planned order... When checking the status in MD04 I can see the old PR with exception 07...
My problem is that this PR is old but it is being processed, therefore i want the system to consider it and not to create new planned order...
I've tried to change configuration of Plan.Horizon and Rescheduling it, but without success...
Can anyone please help me?
Hi,
Can you try executing MRP with planning mode as 3 in MD03 and see the result?
Check and revert back if it solves your problem.
Thank you,
Dipak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Diogo,
You didn't mention any details. However, if the existing PR is fixed, then this issue can arise if your rescheduling horizon is too small. Rescheduling horizon will cause the MRP run to assume reschedule of the existing fixed elements, instead of creating a new planned order. You can review your resched horizon in either OPPQ or OPPR. If this is the culprit, you can alleviate the problem by making the Rescheduling horizon larger.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2c9744af11d182b40000e829fbfe/frameset.htm
Best Regards,
DB49
DB49, thanks for you reply.
I've checked the flag to fix te item in the PR and customized my rescheduling period for a long time and it is still not working...
MRP type is VB and lot size is replenish to maximum stock level...
My rescheduling horizon is set for 365 with tolerance values 2...
My PR is from jul/06/2010.
Any suggestion?
Thanks
Diogo,
Easiest way to see if a PR is fixed is to review in MD04 or MD05. Fixed PRs or Planned orders will have an asterisk next to them.
What is the date/qty of the existing PR?
You ran MRP with parameter "delete and recreate", and it did not delete the PR? That is strange.... What is the doc type of the PR? Item category? Account assignment category? Is it assigned to a source?
What is the date/qty of the new planned order?
What is the Planned delivery time? What is the GR processing time? What is the Purchase Processing time (OMEW)?
Best Regards,
DB49
Hi DB49,
For this material, my reoder point is set to 10 and maximum stock level to 20.
I checked at MD04 and the PR is fixed.
Existing PR date is jul.06/2010 and qty is 300.
I've ran the MRP with Planning Mode 1 because I don't want to delete this PR, I just don't want to create one new Planned order. But just to test it, I've ran with planning mode 3 and the result was the same... Doc type is NB and item category is standard (blank). Account assignment is K (cost center) and it is not assigned to a source.
Date and qty of new planned order is sep.15/2010 and 20...
Both planning delivery time , GR processing time and proc time are set to 1 day.
Thanks.
Account assignment is K
MRP is creating requisition to fill up the stock in your warehouse up to maximum stock level.
Your account assigned purchase requisition does not fill up your warehouse, it is immediatly consumed to a cost center when it arrives, hence MRP has to create a new requisition.