on 09-14-2010 1:02 PM
Hello All,
Now i am creating Purchase Order for XXXX Material. In the purchase order I have mentioned some condition like fright, discount, VAT Etcu2026
Then I am creating one more Purchase Order with same vendor and material combination. In this purchase order all condition will come automatically from old purchase order.
We no need all condition types automatically from old Purchase Order.
Please advise me how I can control
Thanks in advance
Nagi Reddy
Hi,
Spro> MM> Purchasing> Environmental Data> Define Default Values for Buyers
Here Select 01 and Copy as , then go to details of that..
there you can see Tab" Price Adoption"
here choose radio Button for "Do not Copy"
and SAVE it...
Then go to SU01 and Choose "Parameters" Tab..
and in the Parameter ID enter "EVO" and in Parameter Vaue enter the Defaule Value Id you have created
by Copying 01..
and Save it..
Log off & Check..by Creating PO
You will find that, you will not get the Last Price in PO..
Regards
Prabhjot Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
System will always give the same conditions for the same Vendor/Material combination.
You can delete the unwanted conditions manually.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use info rcord of old PO or use refernce of old po for creating new PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.