on 09-14-2010 12:29 PM
Dear friends , good morning !
We are using CO Production Order to collect costs to repair some components used internally.
I´m trying to get the information on google, sap marketplace and even here, but wasn´t conclusive for me if is possible to post labor time in the CO Production order (order type CP01 created at KKF1).
I´m not CO consultant and I´m doing a lot of researches to get this ...
could you please help on this ?
best regards,
Alessandro
Hi
You can use Kb21N to post the activity, nevertheless, from cost center to this CO object
In the field Screen variant, Choose ALL.. then you can see Cost Center and Order fields in the screen...
Enter cost center as sender, your act type, qty and the receiver order.. and SAVE
Regards
Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.