on 09-14-2010 10:04 AM
Hello Gurus,
I am creating process order without material and assigning Production Scheduling Profile in assignment tab. Production Scheduling Profile has release on creation activated in configure, but when I save process order its not released, it remains as CRTD.
When I am creating process order with material as you know Production Scheduling Profile is copied from material master and when I save process order, its automatically released.
I am assigning same Production Scheduling Profile which I am using for second case listed above.
Any ideas?
Thanks
Bhavesh Patel
Hello All,
I am using process order and creating process order using CORO. The configuration is set properly. As par configure, its suppose to release when I create process order and save, but that is not happening. If I create process order with material using COR1, its release when I save after creation in COR1.
Thanks
Bhavesh Patel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Patel,
I Already told, once , you are in order screen, system status will set as CRTD, after that if U assigned, the PSP, It won't work, In case of COR1, material have PSP, If you convert planned order to production, release is triggered in background before the status is created.
If you have still doubt
Create a order in COR1, When you enter the quantity and start date finish date then release is carried out and the status is set as CRTD
in CORO
It is not possible to maintain PSP before entering the qty and Dates
Once U entered the dates, Sytem set the status as created, After you assigna PSP, It won't work
Regards,
Sundaresan
Edited by: Sundaresan . E. V on Sep 14, 2010 7:01 PM
Dear
Please goto OPKP and re-check -Select Production Scheduling Profile -Goto Automatic Action -Hit Rlease Check box -That means you are asking systme to relase the production order once itr is being created .
Now try to create Production Order and once it will created , Relase will happene automatically .By the way , how are you creating Production Order with out material ? Reference to Sales /WBS through CO07??
Is there any user exit running for Production Order Relase for authorisation control ??
Just check in your side and come back
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In Production scheduling Profile, The release setting is checked at that time of order creation,
IN case of production order with out material ,you have assigned the production scheduling profile after the order status as created " CRTD" , SO this seeting won't work for order with out material
Regards,
Sundaresan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Patel,
If the setting or the check box for On Release is included under Automatic Actions --->On Creation,while creating the production
order without material in CO07,after giving the req quantity,date and the settlement parameters the system automatically releases
the order in CO07 itself.
check in OPKP for the prod scheduling profile settings.
Regards
S Mangalraj
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.