Sub contracting stock to consider in MRP

Hi

I want to condiser the stock at sub-cotractor's location to be considered in MRP.

How to do it.

Regards

Prashant

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    Sep 13, 2010 at 09:46 AM

    HI

    Only three type of stocks are considered in MRP maintained in OPPQ

    1. Stock in transfer

    2. blocked

    3.restricted-use stock

    If sub cotractors sloc in is in your plant then you can do thru MMSC and OMIR

    Check and revert

    Regards

    Anupam Sharma

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 13, 2010 at 09:50 AM

    IN Normal MRP, System will consider the sub contracting stock while running MRP

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 13, 2010 at 10:35 AM

    Dear

    If you have maintained MRP type as PD for a material the stock with subcontractor is also being considered as available during MRP run .Please make sure that in SAP T-code OPJJ you should not marked the setting "W/o subcontractors stock

    In standrad MRP , it consider all type of stcok execpt Block Stock

    Hope this is clear

    Regards

    JH

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 21, 2010 at 12:08 AM

    I found the same problem