First step in network planning with SNP

Hi

May I know the first step in network planning with SNP from the following:

1. first step is procurement planning

2. first step is production planning

3. first step is deployment

4. first step is distribution via stock transfers

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Sep 10, 2010 at 06:01 PM

    First step would be master data setup.

    Assuming that is done, then run

    1. SNP Low Level Code

    2. Run Location by Location Heuristics or Network Heuristic for Finished products (will create STRs / Purchase Reqs)

    3. Run PPDS Planning Run or SNP Location Heuristic (depending on material requirement and horizon) to create In-house Production and External Procurement Order

    4. Carry out execution steps for completion of Production and Purchase Orders

    5. Carry out Deployment and TLB to distribute finished products to demand points of the supply chain (where Location Heuristic was first executed)

    Hope this helps.

    Somnath

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.