on 09-10-2010 10:18 AM
Dear PP Experts
While doing backflush in MF42, I am encountering with an error and its desription is Account assignment object is blocked by user
Message RM183 , System error details says When backflushing for an account assignment object for first time, the post processing pointer table RESCO is adjusted, it is currently locked by user, You may also be locking in another seeeion.
This happens only for the first material in the list and it is not saying for the second material onwards during backflush in MF42/ MF42n
Any Idea on this please ?
Regards
PARAMESHWAR
Dear Parmeshwar,
I suspect two persons with different user ids are working on same material ( reservation) at same time
So system is not allowing you
In Std SAP this is not possible
Check in SM12 and delete the lock entries then try again
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mr Madhu,
Thanks for your reply. What I found on this error was, i developed a report, while I am executing the report and this back flush simultaneously, I am encountered with this error. Thanks for the help
Regards
PARAMESHWAR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.