Former Member
Sep 10, 2010 at 01:45 AM

MRP didn't consider Planning Calender while generating the Pur Requisition

601 Views

Hello,

I had a simple scenario of Planning calendar.We set up a Planning Calendar WK1 for Purchase Order to get delivered it on Monday.We assigned it to a raw material.

When we tested it for manually created Purchase Order for particular raw material, it populate the delivery date taking Pl Delivery Time into consideration appropriately on Monday.

But when we ran the MRP for the demand, it did not consider the planning caledar & created the Purchase requisition as per the requirement of the demand of Finished Product where delivery falls on any weekdays.

The MRP Type=PD & lot sizing=PK(Period lot size acc. to plng calendar)

Can you please tell me Why system creates Purchase Requisitions without considering Planning calendar when you run the MRP?

If need any additional inputs,revert.

Thanks in advance.

Pravin