How to block postings to cost centers that have exceeded budget?
How can you make this assessment? Monthly, yearly or both?
Thanks!!
Hi,
The budget in cost centres does not have availability control. You can use a workaround with internal oders. Please, search SDN for this info. No monthly control is possible in standard configuration with this option.
If you choose to implement FM, then budget control flexibility there is quite powerful and you can build whatever logic you want. Just make notice, that the budget won't be managed in cost centres, but in FM objects (fund centres, commitment items, etc.)
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, you can create statistical IO, set budget for it, and while posting to cost center assign that IO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Depends on what feature you are using
If you use funds mngt, you can block postngs to cost centers that exceed the budget.... I guess you can do it montly as well as annually
If you are using Statistical IOs for budgetary control, then ofcourse you can do it at annual level only
Regards
Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.