Hi All
I have created a simple Project with Internal Network Activity (NWA).
Plan Version 0 has been updated with appropriate planned cost.
Partial Confirmation has been posted.
Forecast work is greater than actual work in the Dates TAB of the Internal NWA
Scheduled finish dates are in current period or greater.
When we execute CJ9L no objects are selected for processing? Can anybody please expalin why this may be the case.
I do not believe there is any outsatanding configuration? The costing variants must be working to enable calculation of the Plan Version 0 amount.