09-09-2010 7:07 AM
HI ABAP-EXPERTS,
In Logistics DC view of our MM42(material master change), we need to make changes such taht if RP type is 'ND' or "11' then planning cycle field should have value '1'.
I have already tried with some BADI's suggested in earlier posts, but it seems not to be working.
could anyone please suggest me enhancement for the same?
I would need to do similar chnages to MM46 and MASS_MARC. I will be grateful if anyone can suggest BADI for MM42, MASS_MARC.
Thnks in advance
09-09-2010 11:44 AM
Hi,
Try these Exits:
Enhancement MGW00002 Material Master (Retail): Number Assignment
Alternative Exit:
Enhancement MGW00001 Material Master (Retail): Additional Data
I hope this may helpfull.
Thank you,
Thanks,