on 09-08-2010 11:41 PM
We are running PS with valuated project stock. Our accountants would like to have a monthly balance of all project stock similar to what SAP can produce for plant stock in MC.5. Does anyone know how to do this or something similar?
Hi,
Please check MMBE for Project Stock Or MBBS - valueated Q Stock.
hope this will help you.
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have tried MBBS Tcode. This is meant for that only.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |