how extract data - PS data extraction

Former Member
0 Kudos

Can any one tell me how to extract ps data

Thanks,

Shankar.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

You need to be more specific with your requirements. Assuming you are referring to Project Systems, refer to the below link for a start.

http://help.sap.com/saphelp_nw70/helpdata/en/b9/60073c0057f057e10000000a114084/frameset.htm

Former Member
0 Kudos

Hi,

i need more information about ps-plan,budget,commitment,accurals extraction

Thank you,

Shankar.

Former Member
0 Kudos

Below is a sample PS model that you can implement. Of course, you need to customize based on your requirements. Nevertheless, this should give you a head start.

You can model 2 cubes as stated below.

1. PS Dates (Copy of 0PS_C021):

DataSources:

-0PS_DAT_MLS

-0PS_DAT_NAE

-0PS_DAT_NTW

-0PS_DAT_NWA

-0PS_DAT_PRJ

-0PS_DAT_WBS

2. PS Budget, Planning, Actuals (Z* Cube)

This cube can have 7 feeds; 3 DSO feeds and 4 datasources feeds.

DSO's:

(a) Network Activity: Line-Item Commitment (Copy of 0PS_DS02)

DataSource - 0CO_OM_NWA_3

(b) Project Systems - Planning Data (WBS) (Z* DSO)

DataSource - 0CO_OM_WBS_1

(c) Project Systems - Overall Budget and Plan (Z* DSO)

DataSources - 0CO_OM_WBS_2, 0CO_OM_WBS_3

DataSources:

-0CO_OM_NTW_2

-0CO_OM_NWA_2

-0CO_OM_WBS_6

-0CO_OM_OPA_6

You could then build a multi-provider over Cube 1 and Cube 2 for efficient reporting.

Hope this helps.