cancel
Showing results for 
Search instead for 
Did you mean: 

Project Planning Board

Former Member
0 Kudos

Dear all

i have created a project, with WBS, networks, activities and components. I delete one component and total of the plan is the same before delete the component.

How I show the total plan without the cost of the delete component.

Regards,

Jesús.

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Jesus, have you saved your project after deleting the component from project? If not save the project and then check the PPB again. Also, try other reports and see whether you get right values or not.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jesus,

You can see the plan in S_ALR_87013533 standard report.

Thanks,

Krishna Singh

nitin_patoliya
Active Contributor
0 Kudos

For your component price may be zero value or cost relevancy indicator is not ticked in your component on General data tab.

With Regards

Nitin P.