Skip to Content
avatar image
Former Member

Adding a new tab in activity overview

Hi,

I would like to add a new tab in activity overview (like the "primary costs" existing tab).

Is it possible and how can I do that ?

Thanks for your answers.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Sep 07, 2010 at 10:22 AM

    You can do that in the User Interface Settings in SPRO. Project System->Structures->Network->User Interface Settings->Layout of Activity detail Screen

    Regards,

    Gokul

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      I don't think there is any provisions for it.

      You can goto to ABAPer with CNEX0008 enhancement; ask him if he can call own screen code using this exit. I might work but needs an expert.

      or

      just ask any ABAPer if your requiremnt can be fulfilled with GuiXT.

      Regards,

      Harsh.

  • avatar image
    Former Member
    Sep 07, 2010 at 10:09 AM

    Hi,

    What data you want in the new tab?

    Regards,

    Harsh.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 09, 2010 at 11:31 AM

    Hi,

    You may also think of using the "User fields" for Network activity, which doesnot require any ABAP enhancement.

    Regards

    Sejo

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 22, 2010 at 07:28 AM

    Thanks,

    Add comment
    10|10000 characters needed characters exceeded