on 09-06-2010 6:20 AM
Hi Experts,
I am having a iisue related to Production order
This production order is in closed period ie 2 months back
from this order i want to reject the material order is of 300 qty
out of which 59 qty is rejected and now i want to reverse the production order
It is possible and how ?
This client is in Automotive sector and this happens regularly.
Client want to show the rejection to supplier how to do this without opening back period?
Please suggest.
Pert
Dear ,
Goto MMPV to open the Material Period .I think any business process can hev 2 motnhs material periods open .Please discuss the same with your MM consultant .same way you can do for OB52 to open the FI period because u need to cancal the docuements in MBST .
Both the cases , you have to discuss wit your FI and MM consulatnt who are responsble for maintain materials and FY periods
Regards
JH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Closing thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Part,
As per std SAP u can open the material opening period max 2 month and FI period as per you requirement u can open it.
If your order is 2 month back, so you can contact with MM/FI consultant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.