S_ALR_87013558 with error "Message no. OK602"

Dear experts

When i execute the T-code S_ALR_87013558 for one proj,I came accross the error"No costs, revenues or finances were selected".Double click it,showing:Message no. OK602.

But when i execute the same proj with S_ALR_87013543,I can get all the cost.

How can I solve it? Waiting for your help,thanks.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    Sep 06, 2010 at 05:28 AM

    Robert, S_ALR_87013558 will give budget, actual, commitment where are as S_ALR_87013543 will give Plan Vs Actual. If you have only planned cost at project, but not budget or commitment or actual cost, then S_ALR_87013558 will not show any values but S_ALR_87013543 will give planned cost. Check if your project has budget or actual or commitment cost. If it is not S_ALR_87013558 wil not work in your case.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 06, 2010 at 06:48 AM

    Also you can check whether budget related authorizations are provided or not on your id

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 06, 2010 at 08:22 AM

    Appreciate for your sincerely help.

    As to my id,the authority have no problem.

    Even the proj had actual cost,S_ALR_87013558 will not work all the same.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      S_ALR_87013558, this report will work when only you have budgeted your project, you can verify your project whether it is budgeted or not by using t code CJ31 or in CJ02/CJ03 (in this transaction you can check the status of the WBSE, it must have BUDG in the status)