Hi,

I have a requirement to configure Notification and ECM - Change master together maintaining link.

Also same nr to be maintained for both. How to do it?...

Thanks,

Suresh HP

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Suresh,

Typically, when you process notifications, you can use the 'action box' to execute follow-up functions.In the 'action box' for change notifications,the 'Create ECR/Change Master' option can be used for processing your request.

Regards,

Pradeepkumar Haragoldavar

ulf_petzel
Advisor
Advisor
0 Kudos

Hi,

not sure why this is posted in cFolders forum rather than PLM forum. Or do you look at the Change Number object in cFolders and related notifications?

Please clarify.

Regards, Ulf.