Maintenance Plan

Former Member
0 Kudos

Dear Gurus,

I am creating Single Cycle Plan IP41 where i have given Cycle/ Unit as 1 week, call horizon 90% and scheduling period 365 days. I have gven start cycle date today.

in scheduling the call date is 08-09-2010 and plan date is 09-09-2010. but when i start scheduling the order is created Immediately.

I want the order to be created on Call date. How can go about it please explain.

Regards,

PMAddi

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I am closing this Question as i got the solution from outside the forum.

Regards,

PMAddi

rakesh_mane
Active Contributor
0 Kudos

Hello,

Please let us know how you acheived it

Regards,

Rakesh

rakesh_mane
Active Contributor
0 Kudos

Hello

Please use the Cycle modification factor-->0,65.So order will created on Call date i.e. on 08-09-2010

But your Planned date wills shift to 08-09-2010 also.

Reagrds,

Rakesh

Edited by: RAKESH ASHOK MANE on Sep 3, 2010 12:02 PM

Former Member
0 Kudos

Hi ,

For a new start, or a start in the cycle, despite the scheduling period, the system ensures that at least one date (either with the status "On Hold" or "Called") is generated. Even if the scheduling period is less than the cycle used.For remaining calls like next 03 to 04 calls it they are called then In Maintenance Plan plz tick the completion requirement check box and then again re-strat the plan in IP10 ..

regrds

pushpa