Scenario:
I'm using PP-PI ..4.6c & I'm having trouble sorting out the below issue:
If I have only 2 hours left on a evening shift & the system has scheduled a production operation to start within that 2 hour period but the operation actually takes 4 hours to complete & cannot be stopped (at the end of the shift) after 2 hours & restarted . In reality, the operation would only be started on the morning shift as I have no night shift. Now the operation is behind schedule as I did not start it when scheduled.
How do I get scheduling to ignore the available 2 hours if the production operation is longer than that ? I've tried the distribution keys available in the work centre but with no joy ..or it this dependent on Capacity Levelling??
CJ