on 09-02-2010 1:36 PM
Hi guys.
Someone can help me?
I dont understand that: when I edit a maintenance order of PM and i want display it in PS I using a report for example S_ALR_87013558. The value of the order is in Column "RemOrdPlan".
I thought was a in a column of commitment like a Purchase requisition or a Purchase order.
what is it a column "RemOrdPlan" and when is used?
Tanks for the attention.
Best regards.
tank's alot for your attention
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
They are reserves made in a maintenance order ( this cost doesn't check WBS budget). You can check this cost in RPSCO table with value type 25, is a calculated value because it also depends on the WBS status.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
RemOrdPlan = Plan cost - Actual cost - Committment
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PR/PO/Funds commitment are considered as commitment cost.
Remaining order plan is calculated for a WBSE. It tells how much Order planned cost is remaining for the WBSE.
See 2.b section of this Note 668240 - FAQ 2: Hierarchy reports
Edited by: Ahmed Rifaee on Sep 2, 2010 6:19 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.