No prices could be determined for object Activity type P001/PR01006/1457.

Former Member

Hi,

I'm getting the following error message while working with Easy Cost Planning.

"

No prices could be determined for object Activity type P001/PR01006/1457.

Message no. KW407

Diagnosis

No price could be found for object Activity type P001/PR01006/1457 with price indicator 1 and value type 1.

Procedure

Maintain the price manually or have it determined by the system through the price calculation function.

"

Cost Center: PR01006

Activity type: 1457

Can any respond immediately on this.

Required information of this issue:

Costing Variant (std): PS06

Material Valuation: 4 Planned Price, 2 Std Price, 3 Moving Average Price.

Activity Types/Processes: 1 plan Price for the Period, 6 Most Up-to-date Plan Price.

CO Version Plan/Actual

Sub Contracting: 3 Net Quotation Price.

Quotation In Purchasing : Actual Quota Arrangement

External Processing: 3 Net Quotation Price, 4 Gross Quotation Price

OverHead: No Assignment

And Work Center defined fine had the assignment of Activity type and Cost Center.

In KP26, activity type rate defined for period in combination with Cost center and Activity Type.

Then what would be the problem, pl respond immediately.

Vemula

Accepted Solutions (1)

Accepted Solutions (1)

durgasankar_innamuri
Active Contributor
0 Kudos

Hi,

Cross check routing with KP26.

if the problem is not resolved then check the number ranges are maintained for that groups(KANK).

Regards,

Sankar

Answers (5)

Answers (5)

0 Kudos

Hello,

OKKN - PPC1

OPL1 - PPP1

check the activity tab

at both the place

Plan Price for the Period

this is also a reason other than kp26 price and KANK

0 Kudos

Thanks for your valuable post Vemula.

it helps a lot.

Raghuraj

Former Member
0 Kudos

Hi Friends,

I, my self resolved the issue. by considering the following 3 rd strategy in

For Activity Type/Processes: Considered 3rd strategy as below:

Activity Types/Processes: 1 plan Price for the Period, 6 Most Up-to-date Plan Price

and 2 Plan Price as Average of All Fiscal Year Periods.

Now it has been resolved.

Thanks all.

Now it is closed.

Vemula

former_member187989
Active Contributor
0 Kudos

Search forum with your subject line;You can find lot of answers

Former Member
0 Kudos

Hi Vermula

Go to transaction KP04 and select SAP101. If no customized profile with z exists.

The go to transaction KP06 enter the cost centre, version, periods, and secondary cost element type 43/Activity type per the error and then enter a price and quantity.

I have not done this, but you can let the system calculate a price itself. Maybe the others can offer the solution there.

I hope it helps

Kind regards