Hello,
I've a question regarding capacity in the planning table (MF50).
Our goal is, always having the capacity on the last day for planned and production orders (not matter if it make sense).
Situation:
- Material 1 has In-house Prod. Date = 2 days
- Start screen of MF50
- Tab Scheduling - Prod./basic dates: "Basic dates"
- Tab Scheduling - Scheduling strategy: 2 Backward scheduling
- Tab Scheduling - Capacity planning: flagged
Now, after creating a planned order in MF50, the capacity will be split two days (2 days in-hous prod). But the whole capacity should be on the last day.
I have maintained the distribution keys in customizing (Production --> Repetitive Manufacturing --> Planning --> Planning Table), but without any success.
Has anybody an idea how to maintain this? Is it possible to maintain the planning table in this way?
Thanks,
Martin