on 08-30-2010 2:58 PM
Hi Guru,
I have a tricky question about the APO SNP deployment.
Do you think that it is possible to run the deployment a specific horizon (e.g. 4 weeks for a stock projection) but publishing in R/3 only part of this horizon (e.g. 2 days for the real execution)?
Do you know where is the settings for specifying that the deployment should create purchase orders and not DEP purchase requisitions?
Thanks in advance for your reply,
Regards
A. Mantione
Hi Mantione,
Try using change pointers for data transfer wherein you need to manually
send change pointers to OLTP system against specific dates. The settings
needs to be done under APO customisation under Integration and also under
SNP Configure to OLTP systems
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Senthil,
Is it possible to publish SNP results for specific dates in the planning horizon, say for first one month? Which transaction code is used for such publication settings? How is this customization done? C5 does not have this date feature where as order based publication from collector based on change pointers are possible. Please guide..
Regards,
Raghav
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.