How can used 2 BOMs usage to Run MRP and create Planned Order

0 Kudos

I have a 2 BOM usage need to used when I running MRP after MRP I need plannde order with 2 bom usage

such as... bom usage 1 alt.1

bom usage T alt 1.

When MRP run need to create planned order with bom usage 1 and T

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

It depends how you want to use different BOM in production. You can use the lot size also as selection of BOM or production version too.

Please create different two production versions for same routing with different BOM.

Then in demand management MD61 you can assign the different production versions to PIR. and MRP will plan accordingly.

Or you can use the quota arrangement to plan the requirement on different production version.

Best Regards,

R.Brahmankar

0 Kudos

Thank you from your answer, it's work