on 02-27-2019 5:21 AM
I have a 2 BOM usage need to used when I running MRP after MRP I need plannde order with 2 bom usage
such as... bom usage 1 alt.1
bom usage T alt 1.
When MRP run need to create planned order with bom usage 1 and T
Hello,
It depends how you want to use different BOM in production. You can use the lot size also as selection of BOM or production version too.
Please create different two production versions for same routing with different BOM.
Then in demand management MD61 you can assign the different production versions to PIR. and MRP will plan accordingly.
Or you can use the quota arrangement to plan the requirement on different production version.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.