I have assigned a credit limit to "main segment" for a customer in T-Code : BP

In the configuration, I have assigned the sub-credit control areas to main segment by clicking "Add contribution to main segment".

Now I have set, the credit limit for CFL01 and PFL01 which is assigned to main credit segment 0000.

Now, the main segment limit is defined at 15000 , but the sum total of CFL01+PFL01 = 31030000, in T-Code : BP, and even after the limit is exceeding, it is still being saved and not giving any particular error regarding credit limit of credit control area is more than the main segment, and the values are still being saved. Can anyone help me out, as to what I have missed in the configuration?

My requirement is, as soon as credit limit in credit control area is more than credit limit in main segment, it should give an error that it has exceeded the credit limit of main segment and and should not allow to save the credit limit values.