Hi,

We had a total of, say 100, demands to be planned by CTM. However, CTM terminated after planning about 30 demands. This can be seen from trace file.

CTM internally sorts the demand based on sort criteria & assigns a "demand ID" to each demand & starts processing as per the demand ID.

We could see the following in the appll log:

CTM falls into error with message /SAPAPO/CTM1401

Other terms

SNP PPM; resid; CTM1 401

Reason and Prerequisites

The engine cannot accept Production Process Models maintained with resources whose Mode has no primary resource.

Now, with CTM terminated at demand id =30, we are not able to identify the exact demand (product etc) that CTM stuck with.

Without this, we cannot even check any master data (PPM etc)

Can anybody help?

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Can you check whether note:1022842 suits your issue.