I'm settling the network 230001 under WBS CPA-5321001-01, i encounter following error message:
System status CRTD is active (WBS CPA-5321001-01)
Message no. BS013
Diagnosis
Object WBS CPA-5321001-01 has system status CRTD (Created). According to this status, transaction 'Debit from actual settlement' is not allowed.
Procedure
You can only carry out the requested function if this is allowed according to the status of the object.
but my WBS status is PREL and user staus is APPR BREL WPLI, the edit/status/release menu item is greyed out.
what should I do to settle network 230001? thanks
Hi,
I agree with Nitin. Even though the status is PREL system will still consider it as CRTD. I think you are just opening the relevant WBS and trying to release it. Try to open the entire project and try releasing.
Rest should work fine from here. Revert in case of any issues.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Release all WBS elements and network activities, then execute settlement of the project.
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is standard behaviour as your Project is having PREL System status. ( From business transaction logic perspective system wil count it CRTD ) so, message if correct only. Go to change mode try to release the WBS and than do settlement.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.