on 08-23-2010 11:14 AM
Hi,
I am looking for a table to find all trips that have been assigned different cost elements. PTRV_SCOS only shows the different assignments not the percentage spilt.
In other words I am looking for a report/table that shows the percentage (%) distribution. Field name AUFTL in PR05.
Kind regards,
Frida Kindberg
HI Frida,
The table name is FTPT_REQ_ACCOUNT.
Regards,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yeah I know. But we have a client who want's to know how many of the trips within their company that are assigned to a different cost element than 100% on the default cost center and how many taht are splittet on different cost items. It's just for reporting reasons.
I found out that I can use the sequens number in table PTRV_SCOS and see which trip numbers have more than one line in the cost ditribution. That shows me how many trips that are spilttet into several cost items but that will not show me if a trip is 100% assigned to another cost centre or project or WBS.
Thank you for your helpful answers.
Frida